Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Using microsoft excel and the solver ad in and solver sensitivity report solve t

ID: 3823259 • Letter: U

Question

Using microsoft excel and the solver ad in and solver sensitivity report solve the following question:

Cox Cable Company needs to lease warehouse storage space for five months at the start of the year. It knows how much space will be required in each month. However, since these space requirements are quite different, it may be economical to lease only the amount needed each month on a month-by-month basis. On the other hand, the monthly cost for leasing space for additional months is much less than for the first month, so it may be desirable to lease the maximum amount needed for the entire five months. Another option is the intermediate approach of changing the total amount of space leased (by adding a new lease and/or having an old lease expire) at least once but not every month. Two or more leases for different terms can begin at the same time.

The space requirements (in square feet) and the leasing costs (in dollars per thousand square feet) are given in the tables below.

Month

Space requirements

Lease length

Lease cost

Jan

15,000

1 month

$280

Feb

10,000

2

450

Mar

20,000

3

600

April

5000

4

730

May

25,000

5

820

The task is to find a leasing schedule that provides the necessary amounts of space at the minimum cost.

A.) Determine the optimal leasing schedule and the optimal total cost.

B.) Consider what happens when the cost of a 5-month lease (currently $820) changes. Construct a graph showing how the optimal total cost varies with the cost of a 5-month lease, over the range from $800 to $1000.

C.) Consider instead what happens when the timing of space requirements shifts. In particular, suppose that March requirements drop and April requirements rise by the same amount. Construct a table to show, for shift amounts up to 15,000 square feet, how the shift alters the optimal total cost.

Month

Space requirements

Lease length

Lease cost

Jan

15,000

1 month

$280

Feb

10,000

2

450

Mar

20,000

3

600

April

5000

4

730

May

25,000

5

820

Explanation / Answer

Decision Variables

Length

1

2

3

4

5

Cost

$             280.00

$             450.00

$             600.00

$             730.00

$             820.00

Month

Jan

Feb

Mar

Apr

May

Rqd Sqft

                15,000

                10,000

                20,000

                  5,000

                25,000

Objective Function

Min Cost

$   1,65,00,000

Constraints

Jan

Feb

Mar

Apr

May

Cost

Cost/sq ft

1

0

0

5000

0

10000

$       42,00,000

$                  280

2

0

0

0

0

0

$                      -  

$                     -  

3

0

0

0

0

0

$                      -  

$                     -  

4

0

0

0

0

0

$                      -  

$                     -  

5

15000

0

0

0

0

$   1,23,00,000

$                  820

$                  220

Jan

Feb

Mar

Apr

May

Amounts

15000

15000

20000

15000

25000

>=

>=

>=

>=

>=

Required

15000

10000

20000

5000

25000


a. Determine the optimal leasing schedule. What is the optimal total cost and the corresponding schedule

1 5mo lease in January for 15000 sq ft, 1 1mo lease in Mar for 5000 sq ft, and 1 1mo lease in May for 10000 sq ft. The total cost is $16,500,000.

Decision Variables

Length

1

2

3

4

5

Cost

$             280.00

$             450.00

$             600.00

$             730.00

$             820.00

Month

Jan

Feb

Mar

Apr

May

Rqd Sqft

                15,000

                10,000

                20,000

                  5,000

                25,000

Objective Function

Min Cost

$   1,65,00,000

Constraints

Jan

Feb

Mar

Apr

May

Cost

Cost/sq ft

1

0

0

5000

0

10000

$       42,00,000

$                  280

2

0

0

0

0

0

$                      -  

$                     -  

3

0

0

0

0

0

$                      -  

$                     -  

4

0

0

0

0

0

$                      -  

$                     -  

5

15000

0

0

0

0

$   1,23,00,000

$                  820

$                  220

Jan

Feb

Mar

Apr

May

Amounts

15000

15000

20000

15000

25000

>=

>=

>=

>=

>=

Required

15000

10000

20000

5000

25000


Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote