I In the following MRP planning schedule for Item J, indicate the correct net re

ID: 380078 • Letter: I

Question

I

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)

WEEK NUMBER

I NEED THIS BOTTOM CHART FILLED OUT NOT THE TOP CHART, THANK YOU

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)

Explanation / Answer

The filled up MRP table as below for your reference please :

ITEM :J

LT : 1 WEEK

Q = L4L

PERIOD

1

2

3

4

5

GROSS REQUIREMENT

70

45

65

SCHEDULED RECEIPTS

0

0

0

0

0

PROJECTED AVAILABLE BALANCE:30

30

0

0

0

0

NET REQUIREMENT

0

40

0

45

65

PLANNED ORDER RECEIPT

0

40

0

45

65

PLNNED ORDER RELEASE

40

0

45

65

0

ITEM :J

LT : 1 WEEK

Q = L4L

PERIOD

1

2

3

4

5

GROSS REQUIREMENT

70

45

65

SCHEDULED RECEIPTS

0

0

0

0

0

PROJECTED AVAILABLE BALANCE:30

30

0

0

0

0

NET REQUIREMENT

0

40

0

45

65

PLANNED ORDER RECEIPT

0

40

0

45

65

PLNNED ORDER RELEASE

40

0

45

65

0