I In the following MRP planning schedule for Item J, indicate the correct net re
ID: 380078 • Letter: I
Question
I
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)
WEEK NUMBER
I NEED THIS BOTTOM CHART FILLED OUT NOT THE TOP CHART, THANK YOU
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)
Explanation / Answer
The filled up MRP table as below for your reference please :
ITEM :J
LT : 1 WEEK
Q = L4L
PERIOD
1
2
3
4
5
GROSS REQUIREMENT
70
45
65
SCHEDULED RECEIPTS
0
0
0
0
0
PROJECTED AVAILABLE BALANCE:30
30
0
0
0
0
NET REQUIREMENT
0
40
0
45
65
PLANNED ORDER RECEIPT
0
40
0
45
65
PLNNED ORDER RELEASE
40
0
45
65
0
ITEM :J
LT : 1 WEEK
Q = L4L
PERIOD
1
2
3
4
5
GROSS REQUIREMENT
70
45
65
SCHEDULED RECEIPTS
0
0
0
0
0
PROJECTED AVAILABLE BALANCE:30
30
0
0
0
0
NET REQUIREMENT
0
40
0
45
65
PLANNED ORDER RECEIPT
0
40
0
45
65
PLNNED ORDER RELEASE
40
0
45
65
0