Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

1. A city will undertake four urban renewal housing projects over the next five

ID: 380074 • Letter: 1

Question

1. A city will undertake four urban renewal housing projects over the next five years. Each project has a different timetable. The following table provides the basic data of the situation:

Year 1

Year 2

Year 3

Year 4

Year 5

Cost (million $) for the project

Annual income (million $) if completed 100%

Project 1

Start

End

5.0

0.05

Project 2

Start

End

8.0

0.07

Project 3

Start

End

15.0

0.15

Project 4

Start

End

1.2

0.02

Budget (million $)

3.0

6.0

7.0

7.0

7.0

Projects 1 and 4 should be finished completely within their durations. The remaining two projects can be finished partially within budget limitations if necessary; however, each project must be at least 30% completed within its duration. At the end of each year, the completed section of a project is immediately occupied by tenants, and a proportional amount of income is realized afterwards.

For example, if 40% of project 1 is completed in year 1 and 60% in year 3 (i.e. nothing is completed in year 2), the associated income over this 5-year planning horizon is calculated as follows:

Year 1 income = 0

Year 2 income = 0.4 × $50,000

Year 3 income = 0.4 × $50,000

Year 4 income = (0.4 + 0.6) × $50,000

Year 5 income = (0.4 + 0.6) × $50,000.

As to the cost of the project, it can be prorated; for example, if 40% of project 1 is scheduled to be completed in year 1, the cost needed in year 1 for the project is 0.4 × $5,000,000. The budget arranged by the city each year for these projects is shown at the bottom of the above table.

Develop a schedule for these four projects, indicating their progress for each year that will maximize the total income over the 5-year horizon.

Year 1

Year 2

Year 3

Year 4

Year 5

Cost (million $) for the project

Annual income (million $) if completed 100%

Project 1

Start

End

5.0

0.05

Project 2

Start

End

8.0

0.07

Project 3

Start

End

15.0

0.15

Project 4

Start

End

1.2

0.02

Budget (million $)

3.0

6.0

7.0

7.0

7.0

Explanation / Answer

Step 1 identify the per million return rate:

Step 2 set priority as per return rate:

The investment schedule is found out,

as per the priority and start and end, with the budget in place:

So the return corresponding to it are:

Year 1 Year 2 Year 3 Year 4 Year 5 Cost (million $) for the project Annual income (million $) if completed 100% Per million return Priority Project 1 Start End 5 0.05 0.01 2 Project 2 Start End 8 0.07 0.00875 4 Project 3 Start End 15 0.15 0.01 3 Project 4 Start End 1.2 0.02 0.016667 1 Budget (million $) 3 6 7 7 7