7. Fancy Trends Inc., a handbag manufacturing company, assembles handbags in an
ID: 379586 • Letter: 7
Question
7. Fancy Trends Inc., a handbag manufacturing company, assembles handbags in an assembly line using 10 workstations. The target output for an 8-hour workday is 120 bags. The sum of the task times is 30 minutes/bag. The cycle time is 4 minutes/bag. The assembly-line efficiency is ______ .
a.
65%
b.
70%
c.
75%
d.
80%
85%
8.
According to your textbook, the determination of specific job tasks and
responsibilities is/are called _____ .
a. Job design
b. Ergonomics
c. Job enlargement
d. Job enrichment
e. Job-knowledge gap analysis
9. Based upon your reading of the textbook, which of the following is not a disadvantage of virtual teams?
a. Security
b. Equipment changeover and sharing
c. Synchronizing calendars
d. Socialization
e. Working hours
a.
65%
b.
70%
c.
75%
d.
80%
85%
8.
According to your textbook, the determination of specific job tasks and
Explanation / Answer
PLEASE FIND ANSWER TO QUESTION NO 7:
Assembly Line efficiency
= Sum of task times in all workstations / ( Number of workstation x Cycle time ) x 100
= 30/ ( 4 x 10) x 00
= 30/40 x 100
= 75%
THE ASSEMBLY LINE EFFICIENCY = 75%
Job design is the function of specifying the work activities of an individual or group in an organizational setting. The objective of job design is to develop jobs that meet the requirements of the organization and its technology and that satisfy the jobholder's personal and individual requirements. Thus correct answer is “Job Design “
THE ASSEMBLY LINE EFFICIENCY = 75%