Question
Secur ittps//canvas edu/courses/30150/q Q tion 50 0.4 pts If each task (with ne time each task takes to do given in minutes) in the continuously operating sequential process below is assigned to a different person (there are five workers in all, one for each task), what is the maximum output per hour that is possible from this system? 15 min 10 min 6 min 20 min 9 mia Unable to determine from the information provided 1 unit/hour O 9 units/hour 20 units/hour O 3 units/hour Honorlock is sharing your scExplanation / Answer
The correct choice is 1 unit / hour
Explanation : - The production of 1 unit consists of 5 tasks and each task is assigned to one person and in total there are 5 persons to complete the 5 tasks . The sum of the task times equals 15 mins + 10 mins + 6 mins + 20 mins + 9 mins i.e. 60 mins .
Thus one unit is produced in 60 minutes or 1 hour.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.