1. Your primary responsibility as a systems analyst concerns Please provide your
ID: 3775141 • Letter: 1
Question
1.
Your primary responsibility as a systems analyst concerns
Please provide your answer in the rich text box.
A
People
B
Hardware
C
Application software development
D
Controls
E
Documentation and training materials
2.
Greater user involvement in the system development process usually results in ____.
Please provide your answer in the rich text box.
A
Poorer communication
B
More satisfied users
C
Slower development times
D
Both b and c
3.
The first step in creating a WBS is to ____.
Please provide your answer in the rich text box.
A
Mark all recognizable events
B
Determine time requirements
C
Identify all tasks
D
Estimate task completion time and cost
4.
As a rule of thumb estimate, what percentage of the entire development effort should be devoted to the project initiation and planning process?
Please provide your answer in the rich text box.
A
Between 10 and 20 percent
B
Less than 5 percent
C
Less than 10 percent
D
Between 20 and 30 percent
E
Over 50 percent
5. In the ____, the result of each phase, which is called a deliverable or end product, flows sequentially into the next phase in the SDLC.
A
Interactive model
B
Requirements model
C
Waterfall model
D
Object model
6.
The trained individual who plans and leads joint application design sessions is referred to as the
Please provide your answer in the rich text box.
A
Scribe
B
Session leader
C
Manager
D
Analyst
E
Sponsor
7.
The typical participants in a JAD include
Please provide your answer in the rich text box.
A
The CEO
B
A city official
C
A systems analyst
D
A customer
E
Academic faculty
8.
An example of a project management system is
Please provide your answer in the rich text box.
A
Word Perfect
B
Microsoft Office
C
Microsoft Project for Windows
D
Lotus 1-2-3
E
QuarkXpress
9.
What would be the estimated time for completion if time estimates for programming are as follows? optimistic = 4 weeks; pessimistic = 6 weeks; realistic = 5 weeks
Please provide your answer in the rich text box.
A
5 weeks
B
6 weeks
C
15 weeks
D
3 weeks
E
30 weeks
10.
The primary deliverable from the project identification and selection phase is
Please provide your answer in the rich text box.
A
A context data flow diagram
B
At least three substantively different system design strategies for building the replacement information system
C
The development of a new version of the software and new versions of all design documents
D
An entity relationship diagram
E
A schedule of specific IS development projects
Your primary responsibility as a systems analyst concerns
Please provide your answer in the rich text box.
A
People
B
Hardware
C
Application software development
D
Controls
E
Documentation and training materials
Explanation / Answer
1) Your primary responsibility as a systems analyst concerns application software development.
2) Greater user involvement in the system development process usually results in more satisfied users and slower development times
3) The first step in creating a WBS is to identify all tasks
4) As a rule of thumb estimate, the percentage of the entire development effort to be devoted to the project initiation and planning process should be between 10 and 20 percent
5) In the Waterfall model, the result of each phase, which is called a deliverable or end product, flows sequentially into the next phase in the SDLC.
6) The trained individual who plans and leads joint application design sessions is referred to as the session leader
7) The typical participants in a JAD include a session leader, a scribe and a sponsor
8) An example of a project management system is microsoft office.
9) C
10) The primary deliverable from the project identification and selection phase is a schedule of specific IS development projects