Based on \" Hospital Management Project \", Answer the following questions : Q 1
ID: 3774670 • Letter: B
Question
Based on " HospitalManagement Project ", Answer the following questions :
Q 1: A methodology describes how things should be done, design a table showing how you can map the main activities of "Hospital Management Project "into the knowledge areas ? [2 Marks]
Q 2: Using Microsoft Project 2007/2010 tool, draw Gantt Chart for " HospitalManagement Project ",showing the Task name (Work Breakdown Structure (WBS) )and the duration of each task ? [2 marks]
Q 3: Design a table showing the Project Scope Management Summaryfor " HospitalManagement Project " [1 Mark]
Explanation / Answer
Q 1: A methodology describes how things should be done, design a table showing how you can map the main activities of "Hospital Management Project "into the knowledge areas ?
Answer:)
Hospital Management considers the distinct seperation of general administration from clinical management,with the former requiring experts in general management concerns such as finance ,administration and marketing among others while the latte in medical and clinical care matters .The two aspects must coordinate.
These are the steps involved in hospital management:
Step1:Determine needs and review the hospital services in the area:
The first step requires determines and understandin the main issues and problems related to the needs of a organization for hospital care and management services.
Step 2: Identify stake holders and thier roles
Step 3: Develop an implementation pla for the public -private patnership in hospital management
Step 4:Developing a marketing and promotipn plan.
Step 5: Conduct procurement
Step 6: Implement the publec and private partnership
Q 2: Using Microsoft Project 2007/2010 tool, draw Gantt Chart for " HospitalManagement Project ",showing the Task name (Work Breakdown Structure (WBS) )and the duration of each task ?
Answer:)
Work Breakdown Structure (WBS)
ACTIVITY
DESCRIPTION
PREDECESORS
DURATION (WEEKS)
1
Select administrative and medical staff
12
2
Select site and do site survey.
10
3
Select equipment
1
10
4
Prepare final construction plan and lay out
2
05
5
Purchase and take delivery of equipments
3
20
6
Bring utilities to the site
2
15
7
Construct the hospital
3
10
8
Develop an information system
1
10
9
Install the equipment
1,2,3
20
Q 3: Design a table showing the Project Scope Management Summaryfor " HospitalManagement Project "
Answer:)
Project Scope Managenemt Summaryfor " HospitalManagement Project "
Role
Description
Project Sponsor
Provides executive team approval and sponsorship for the project.
Has budget ownership for the project and is the major stake holder and recipient for the project deliverables.
Project Director
Provides overall management to the project. Accountable for establishing a Project Charter, developing and managing the work plan, securing appropriate resources and delegating the work and insuring successful completion of the project. All project team members report to the project manager. Handles all project administrative duties, interfaces to project sponsors and owners and has overall accountability for the project
Steering
Committee
Provide assistance in resolving issues that arise beyond the project manager’s jurisdiction. Monitor project progress and provide necessary tools and support when milestones are in jeopardy.
Steering
Committee
Key provider of requirements and recipient of project deliverable and associated benefits. Deliverable will directly enhance the stakeholders’ business processes and environment. Majority of stakeholders for this project will be agency leads, CIO’s, and project management representatives.
ACTIVITY
DESCRIPTION
PREDECESORS
DURATION (WEEKS)
1
Select administrative and medical staff
12
2
Select site and do site survey.
10
3
Select equipment
1
10
4
Prepare final construction plan and lay out
2
05
5
Purchase and take delivery of equipments
3
20
6
Bring utilities to the site
2
15
7
Construct the hospital
3
10
8
Develop an information system
1
10
9
Install the equipment
1,2,3
20