A firm may choose to implement a Project Management Methodology in order to impr
ID: 377211 • Letter: A
Question
A firm may choose to implement a Project Management Methodology in order to improve Project Consistency Project Comparability Project Efficiency Project Effectiveness Any or all of the above:
p
roject Consistency
Project Comparability
Project Efficiency
Project Effectiveness
Any or all of the above
What is the slack for a task on a project plan's critical path?
Less than 0
0
Greater than 0
Could be any of the above
What type of contract is most likely to motivate a service provider to move slow and bill as many hours as possible?
Not to Exceed
Fixed Price
Time and Materials
Less than 0
0
Greater than 0
Could be any of the above
What type of contract is most likely to motivate a service provider to move slow and bill as many hours as possible?
Not to Exceed
Fixed Price
Time and Materials
Explanation / Answer
Answer e. Any or all of the above takes care of any of the other 4 options. Apart from that option 'c' is one solution
Answer d. It takes care of any option. Adittionally b. zero is the answer
Answer c. Time and Materials