Question

Understanding MPS:

Part1

The master production schedule is related to MRP and the production plan in that:

I: The MPS drives the production plan
II: The MPS disaggregrates the production plan
III: The MPS is the starting point for MRP

Which combination of statement(s) is true?

a). II only
b). II and III only
c). I and II only
d). I, II, and III

Part2

Typical uses of master schedule activity include which of the following?

I: Driving a material requirements planning system
II: Planning future production
III: Employing rough-cut capacity planning
IV: Establishing the production plan

Which combination of use(s) are correct?

a). I only
b). II and III only
c). I, II, and III only
d). I, II, III, and IV

Explanation / Answer

Part 1 Answer - d (I, II, and III) are true statements

MPS is the master production schedule is the basically comes from the customer and it contains the customer sales order demand. This demand needs to produced to meet the customer demand. For this the MRP is run for achieving the demand as per master production schedule. Hence MPS drives the production plan, as the input from MPS comes into production plan. MRP is planning material resource planning for meeting the customer demand generated in MPS. hence MPS is the starting point for the MRP.

Part 2 Answer - c (I, II, and III only) statements are true.

Master Scheduel activity drives the MRP, as it is the input for the MRP and the base of MRP is to meet the demand generated by Master schedule activity. The Master schedule activity can be used for future production plan as it helps to give the information of future demands. The information provided by the master Schedule activities can be used for developing the future rough cut capacity planning, as the rough cut capacity planning needs the information of demand which comes from the master scheduler activity.