Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question 17 ) The president of a consulting firm wants to minimize the total num

ID: 375395 • Letter: Q

Question

Question 17) The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants—Charlie, Gerald, Johnny, and Rick—to complete any of the four projects, as follows:

Project Hours

Consultant

A

B

C

D

Charlie

13

16

11

18

Gerald

13

15

10

12

Johnny

15

11

20

15

Rick

17

17

12

22

What is the optimal assignment of consultants to projects? (Use the assignment method.)

Question 21) A manufacturing company preparing to build a new plant is considering three potential locations for it. The fixed and variable costs for the three alternative locations are presented below.

a. Complete a numeric locational cost-volume analysis.

b. Indicate over what range each of the alternatives A, B, C is the low-cost choice.

c. Is any alternative never preferred? Explain.

Costs

A

B

C

Fixed ($)

2,500,000

2,000,000

3,500,000

Variable ($ per unit)

21

25

15

Project Hours

Consultant

A

B

C

D

Charlie

13

16

11

18

Gerald

13

15

10

12

Johnny

15

11

20

15

Rick

17

17

12

22

Explanation / Answer

17.

The problem is of minimization

Intially to solve the problem by assignment method.

Let us consider as:

Further, let is rename the jobs of consultants as:

A: I

B: II

C : III

D : IV

SOLUTION:

Solution:
The number of rows = 4 and columns = 4

  

I

II

III

IV

   

A

13

16

11

18

B

13

15

10

12

C

15

11

20

15

D

17

17

12

22

   



Here given problem is balanced.

Step-1: Find out the each row minimum element and subtract it from that row

  

I

II

III

IV

   

A

2 2=13-11

5 5=16-11

0 0=11-11

7 7=18-11

(-11)

B

3 3=13-10

5 5=15-10

0 0=10-10

2 2=12-10

(-10)

C

4 4=15-11

0 0=11-11

9 9=20-11

4 4=15-11

(-11)

D

5 5=17-12

5 5=17-12

0 0=12-12

10 10=22-12

(-12)

   



Step-2: Find out the each column minimum element and subtract it from that column.

  

I

II

III

IV

   

A

0 0=2-2

5 5=5-0

0 0=0-0

5 5=7-2

B

1 1=3-2

5 5=5-0

0 0=0-0

0 0=2-2

C

2 2=4-2

0 0=0-0

9 9=9-0

2 2=4-2

D

3 3=5-2

5 5=5-0

0 0=0-0

8 8=10-2

   

(-2)

(-0)

(-0)

(-2)



Step-3: Make assignment in the opporunity cost table
(1) Rowwise cell (C,II) is assigned

(2) Rowwise cell (D,III) is assigned, so columnwise cell (A,III),(B,III) crossed off.

(3) Columnwise cell (A,I) is assigned

(4) Columnwise cell (B,IV) is assigned


Rowwise & columnwise assignment shown in table

  

I

II

III

IV

   

A

[0] (3) Column wise cell (A,I) is assigned

5

0 Column wise (A,III) crossed off because
(2) Row wise cell (D,III) is assigned

5

B

1

5

0 Column wise (B,III) crossed off because
(2) Row wise cell (D,III) is assigned

[0] (4) Column wise cell (B,IV) is assigned

C

2

[0] (1) Row wise cell (C,II) is assigned

9

2

D

3

5

[0] (2) Row wise cell (D,III) is assigned
so columnwise cell (A,III),(B,III) crossed off.

8

   



Step-4: Number of assignments = 4, number of rows = 4
Which is equal, so solution is optimal

Optimal assignments are

  

I

II

III

IV

   

A

[0] Original cost 13

5 Original cost 16

0 Original cost 11

5 Original cost 18

B

1 Original cost 13

5 Original cost 15

0 Original cost 10

[0] Original cost 12

C

2 Original cost 15

[0] Original cost 11

9 Original cost 20

2 Original cost 15

D

3 Original cost 17

5 Original cost 17

[0] Original cost 12

8 Original cost 22

   



Optimal solution is

Work

Job

Cost

A

I

13

B

IV

12

C

II

11

D

III

12

Total

48

Let us now rename again in the final table:

Work

Job

Cost

Charlie

A

13

Gerald

D

12

Johnny

B

11

Rick

C

12

Total

48

Hence, the assignments to consultants to be allocated as above table to minimize the total number of hours as:

Charlie: A

Gerald: D

Johnny: B

Rick: C

21.

Hence, B is cheapest up to 125,000 units; C is cheapest after 166,667 units. A is cheapest in between. The B-C crossover is not relevant.

  

I

II

III

IV

   

A

13

16

11

18

B

13

15

10

12

C

15

11

20

15

D

17

17

12

22

   

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote