Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Earliest and latest times for each activity are calculated by usung the forward-

ID: 374173 • Letter: E

Question

Earliest and latest times for each activity are calculated by usung the forward-pass and backward-pass method to find out the critical path.

Critical path is defined as the longest path from start to end and or made up of critical activities (having zero slack).

A Precedence Diagramming Method (PDM), which is sometimes also known as the Activity on Node (AON) Diagramming Method, is a graphical representation technique, which shows the inter-dependencies among various project activities.

Calculations are as follows:

C

After crashing activity L by three days, there is no other critical path.

Revised table is as follows:

Activity Predecessor Estimated Duration Earliest Start-ES Earliest Finish-EF Latest Start-LS Latest Finish-EF Slack = LF-ES-D A 2 0 2 0 2 0 Critical B 3 0 3 22 25 22 C 3 0 3 22 25 22 D A 3 2 5 2 5 0 Critical E D 3 5 8 5 8 0 Critical F E 2 8 10 8 10 0 Critical G F 3 10 13 12 15 2 H F 5 10 15 10 15 0 Critical I G, H 6 15 21 15 21 0 Critical J G 2 13 15 21 23 8 K H 4 15 19 17 21 2 L I, K 4 21 25 21 25 0 Critical M J 2 15 17 23 25 8 Critical path is Start--A--D--E--F--H--I--L--Finish , duration is 25 (2+3+3+2+5+6+4)

Explanation / Answer

Draw (sketch) this network manually as a PDM network.

2.         What is the critical path and the total project duration?

3          Which activity has the largest slack?

4.         Crash the project by 3 days and re-identify the critical path?

Activity

Predecessor

Estimated Duration

A

2

B

3

C

3

D

A

3

E

D

3

F

E

2

G

F

3

H

F

5

I

G, H

6

J

G

2

K

H

4

L

I, K

4

M

J

2

Activity

Predecessor

Estimated Duration

A

2

B

3

C

3

D

A

3

E

D

3

F

E

2

G

F

3

H

F

5

I

G, H

6

J

G

2

K

H

4

L

I, K

4

M

J

2

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote