Johnson’s Rule is: Repeat steps 1,2 and 3 filling in the schedule from the front
ID: 373503 • Letter: J
Question
Johnson’s Rule is:
Repeat steps 1,2 and 3 filling in the schedule from the front and the back until all jobs have been scheduled
Accordingly schedule of jobs as follows :
C ------ > B -------- > E -------- > A ---------- > D ------------- > F
CALCULATIONS
Operation 1 : C ( 5) B (13) E( 22) A( 34) D ( 40) F ( 43)
Operation 2 : C ( 19) B( 30) E ( 40) A(44) D ( 46) F ( 44)
(time in parenthesis is cumulative hours to complete)
It will take 44 hours to complete all THE jobs
Scheduled Order
Job
1
C
2
B
3
E
4
A
5
D
6
F
THE TOTAL LENGTH OF TIME TAKEN TO COMPLETE THE SIX JOBS ( USING 2ND OPERATION) = 44 HOURS
Scheduled Order
Job
1
C
2
B
3
E
4
A
5
D
6
F
Explanation / Answer
Using Johnson's rule for 2-machine scheduling, the sequence is: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Scheduled Order Job Operation2 (hours) Job (hours) 12 14 10 For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation)-hours (enter your response as a whole number)