Yes, Answer is E. All of the above Primary Report Concern production & inventory
ID: 373297 • Letter: Y
Question
Yes, Answer is E. All of the above
Primary Report Concern production & inventory planning and control which include schedule of planned order which indicated the amount & time of future order, order releases which help to execute the planned order and change to planned order is a revision of due dates & quantity.
Secondary report concern about performance where include evaluation system operation find out the missed delivery & stock out, planning report is forecast the future inventory requirement and exception report is concern attribute the major discrepancies .
Explanation / Answer
Typical output reports from a material requirements planning system include
I think the correct answer is E. but i would like to make sure i am correct.
Thank you for the help
A. MRP by period report.Related Questions