Basis the information, Quantity and Price slabs are:
0 to 750
750 to 900
900 and above
The EOQ for 1st slab is 800
EOQ for 2nd slab is 875
EOQ for 3rd slab is 925
Now, the 1st slab value of EOQ is out of range, for 2nd slab the value is in range and also for 3rd slab. But the information is not complete about ordering cost, holding cost. The Optimal quantity in discount models is determined basis total cost which is the function of Holding cost + ordering cost + Product cost.
So, all these costs are important to find EOQ
Explanation / Answer
Exercise 11: In the calculation of an optimal policy for an all-units discount schedule, you first compute the EOQ values for each of the three order costs, and you obtain: QC0) 800, Q(1) 875, and Q(2) 925. The all-units discount schedule has breakpoints at 750 and 900. Based on this information only, can you determine what the optimal order quantity is? Explain your answer.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.