1) Based on the following, convert the outline WBS into another WBS format (Org

ID: 372452 • Letter: 1

Question

1)    Based on the following, convert the outline WBS into another WBS format (Org Chart or Mind Map), and then create the network diagram (AON). Calculate the PERT for each activity in yellow.

(You may have to save it as an image and insert the picture file)

Activity

Predecessor

Estimated time (PERT)

Start

Opt

Most

Pest

PERT Estimate

1.0 A

?

?

?

?

1.1 A1

Start

1D

3D

4D

?

1.2 A2

Start

2D

3D

4D

?

1.3 A3

Start

1D

1D

4D

?

2.0 B

2.1 B1

A1, A2

2.2 B2

A3

3.0 C

3.1 C1

B1, B2

4.0 D

4.1 D1

B2

4.2 D2

B2

4.3 D3

D2

5.0 E

?

?

?

?

5.1 E1

C1

4D

7D

13D

?

6.0 F

6.1 F1

D1, D3

7.0 G

7.1 G1

E1, F1

End

G1

Activity

Predecessor

Estimated time (PERT)

Start

Opt

Most

Pest

PERT Estimate

1.0 A

?

?

?

?

1.1 A1

Start

1D

3D

4D

?

1.2 A2

Start

2D

3D

4D

?

1.3 A3

Start

1D

1D

4D

?

2.0 B

2.1 B1

A1, A2

2.2 B2

A3

3.0 C

3.1 C1

B1, B2

4.0 D

4.1 D1

B2

4.2 D2

B2

4.3 D3

D2

5.0 E

?

?

?

?

5.1 E1

C1

4D

7D

13D

?

6.0 F

6.1 F1

D1, D3

7.0 G

7.1 G1

E1, F1

End

G1

Explanation / Answer

PERT estimate is the weighted mean of three time estimates with weights 1, 4, 1 respectively

PERT estimate = (Opt+4Most+Pest)/6

For 1.A times are Maximum of times of A1, A2, A3

Start A A1 A2 A3 B B1 B1 B2 B2 B2 C C1 C1 D D1 D2 D3 E E1 F F1 F1 G G1 G1 End