54. In which organizational form is the project manager least Ikely to share res

ID: 372309 • Letter: 5

Question

54. In which organizational form is the project manager least Ikely to share resources with other projects a. classical b. traditional c. strong matrix d. weak matric e projectized 55. Who creates the WBS? a. project manager b. project manager and project champion c. upper management in the performing organization d. the customer e. project manager with help from the project team 56. All of the following are true about a project, except a. Cost is low and stakeholder influence is highest in the beginning b. Staffing levels and the ability to influence the product characteristics are both low at the end of the project c. When the project is executing, both cost and stakeholders' influence are at the highest d. Uncertainty is at its highest at the beginning of the project e. None of the above, all apply 57. Ellen is responsible for writing chapters 6, 8, and 10 of a book. She can do them in any order. This is an example of a. an assumption b. an externmal dependency c. a discretionary dependency d. a resource constraint e. none of the above 58. For the figure shown, what duration would the critical path be if the relationship between B and D were Start-to-Start (SS)? a. 29 days b. 28 days c. 27 days d. 32 days e. none of the above 45 C7 H2 E3 F4 67 59. A program is considered to be: a. b. c. d. e. a part of a project that is mandated by the government a strategy for identifying project risks usually a fast-track path for a new project manager a collection of related projects two or more phases of a project 60. Consider the following network diagram. Which of the following is the critical path? a. Start-C-D-E-Finish b. Start -I-G-E-Finish c. Start-I-G-H-Finish d. Start-I-J-H-Finish e. Start-C-G-H-Finish Start

Explanation / Answer

54) D

In weak matric, the project is handled mainly by functional manager and project manager has part time role. So, there are lesser chances of sharing the resources

55) E

It is created by Project manager so as to break down work which needs to be carried out by the team. However, team also gives input for all tasks which needs to be covered

56) B

Staffing level are low at the beginning and high at the end of the project and team is firmed and work hard to achieve the timelines

57) C

It is the discretion to decide which chapter to write first. However it is better to write in sequence as reference can be given on later chapters about previous chapter. So, it is advisable but not strict to follow