Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Jean Walker is making plans for spring break at the beaches in Florida. In apply

ID: 371019 • Letter: J

Question

Jean Walker is making plans for spring break at the beaches in Florida. In applying techniques she learned in her quantitative methods class, she has identified the activities that are necessary to prepare for her trip. The following table lists the activities and the immediate predecessors.

Activity

Immediate Predecessors

A

B

A

C

A

D

B

E

C,D

F

A

G

E,F

The following are the activity times for Jean Walkers activities. Find the earliest, latest, and slack times for each activity. Then find the critical path.

Activity

Time (in days)

A

3

B

7

C

6

D

2

E

5

F

8

G

4

Activity

Immediate Predecessors

A

B

A

C

A

D

B

E

C,D

F

A

G

E,F

Explanation / Answer

Following is the precedence diagram of activities :

                                                                                A

                     B

                        C

                 F

                    D

                                                              E

                                                                                G

The possible parallel paths and their cumulative durations as follows :

A-B-D-E-G = 3 + 7 +2 + 5 + 4 = 21

A-C-E-G = 3 + 6 + 5 +4 = 18

A-F-G = 3 + 8 +4 = 15

Out of above, A-B-D-E-G has the longest duration and hence forms the Critical path

It is to be noted that Slack Times for all activities on Critical Path are ZERO .

Slack is defined as Difference Between Late Start ( LS) and Early Start ( ES) times or difference between Late Finish ( LF) and Early Finish ( EF ) time .

Slack of activity C

= Duration of path A-B-D-E-G ( CRITICAL PATH ) – Duration of path A-C-E-G

= 21 – 18

= 3 days

Slack of activity F

= Duration of path A-B-D-E-G ( CRITICAL PATH ) – Duration of path A-F-G

= 21 – 15

= 6 days

Activity

ES

LS

EF

LF

Slack

A

0

0

3

3

0

B

3

3

10

10

0

C

3

6

9

12

3

D

10

10

12

12

0

E

12

12

17

17

0

F

3

9

11

17

6

G

17

21

17

21

0

                                                                                A

                     B

                        C

                 F

                    D

                                                              E

                                                                                G

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote