IT Project Management IT270
Question 1
A. project has five stakeholders, when an additional project member gets added, how many communication channels exist?
b. The project manager intends to get a module completed within a deadline but there are few reluctant team members who don’t intend to comply with the manager. What strategies can the manager use to resolve the potential disagreements?
Question 2
A. Define risk utility. How can we categorize people as risk-averse, risk-seeking or risk neutral on the basis of risk utility.
b. Explain how risk quantification can be done using the probability/impact matrices. Draw a sample probability/impact matrix to illustrate the concept.
Explanation / Answer
Solution:
Note: The first question is done as per Chegg guidelines, please repost others. ?
1)
A
The stakeholders can be considered as the nodes in the graph and the channels are like edges in the graph
so maximum they can be with n stakeholders = n(n-1)/2
currently, there are 5
and when one has added it becomes 6
so total number of communication channles= 6*5/2 = 15
B)
The strategies which can be followed are:
I hope this helps if you find any problem. Please comment below. Don't forget to give a thumbs up if you liked it. :)