assuming the earliest starting time for a b and c is zero. please explain each p
ID: 370621 • Letter: A
Question
assuming the earliest starting time for a b and c is zero. please explain each part thanks!
Explanation / Answer
Early start of A = 0
Early finish of A = 0 + 3 (3)
Early start of B = 0
Early finish of B = 0+4 ( 4)
early start of C = 0
early finish of C = 0 + 2 ( 2)
early start of D = max early finish of A,B ( 4)
early finish of D = 4 + 3 ( 7)
early start of E = max early finish of A,C ( 3)
early finish of E = 3+ 5 ( 8)
early start of F = early finish of D ( 7)
early finish of F = 7 + 6 ( 13)
early start of G = early finish of D ( 7)
early finish of G = 7 + 5 ( 12)
early start of H = early finish of E ( 8)
early finish of H = 8 + 4 ( 12)
Latest finish of H = 12
latest start of H = 12 - 4 ( 8)
Latest finish of G = 12
latest start of G = 12 - 5 ( 7)
latest finish of F = 13
latest start of F = 13 - 6 ( 7)
latest finish of E = latest start of H (8)
latest start of E = 8 - 5 ( 3)
latest finish of D = minimum latest start of f,g ( 7)
latest start of D = 7 - 3 ( 4)
latest finish of C = latest start of E ( 3)
latest start of C = 3 - 2 ( 1)
latest finish of B = latest start of D ( 4)
latest start of B = 4 - 4 ( 0)
latest finish of A = minimum latest start of D , E ( 3)
latest start of A = 3 - 3 ( 0)
The critical path is A-B-D-E-F-G-H
The project completion time is the sum of the activity times of the critical path = 30
________________________________________________________________
If activity D finishes at time 8, the project will be delayed because the latest finish of activity D is 7 and activity D has no slack .
___________________________________________________________________________
If activity E is reduced to 4 , the project completion time will decrease as the new critical path will be B-D-F-G-H.
The project completion time will be = 22
Activity Early start Early finish Latest start Latest finish Slack A 0 3 0 3 0 B 0 4 0 4 0 C 0 2 1 3 1 D 4 7 4 7 0 E 3 8 3 8 0 F 7 13 7 13 0 G 7 12 7 12 0 H 8 12 8 12 0Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.