Develop a lot-for-lot solution and calculate total relevant costs for the gross

ID: 368440 • Letter: D

Question

Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table* Period Gross requirements20 1 23 4 5 6 7 89 10 11 12 40 0 70 3010 80 50 "Holding cost = $2.50/unitweek setup costs S200: lead time: 1 week; beginning inventory : 40 Develop a lot-for-lot solution (enter your responses as whole numbers). Period Gross requirements On-hand at beginning of period On-hand at end of period Order receipt Order release 1 2 3 4 5 6 78 9 10 11 12 20 40 40 70 30 10 80 50 40

Explanation / Answer

The MRP table for Lot-for -Lot solution is presented below :

Beginning inventory : 40

                                                              Week

Lot size: Lot for Lot

Lead time: 1 week

1

2

3

4

5

6

7

8

9

10

11

12

Gross Requirement

20

0

40

0

40

70

30

0

10

80

0

50

On hand at beginning of period : 40

40

20

20

0

0

0

0

0

0

0

0

0

On hand at end of period

20

20

0

0

0

0

0

0

0

0

0

0

Planned order receipt

0

0

20

0

40

70

30

0

10

80

0

50

Planned order release

0

20

0

40

70

30

0

10

80

0

50

0

Following have been considered while developing above Lot-for-Lot solution :

i)On hand at beginning of period 1 = 40

On hand at beginning of period t+1 = On hand at end of period t

ii) On hand at end of period t = On hand at beginning of period t – Gross requirement for period t

( when On hand inventory at beginning of period t > Gross requirement for period t)

In such case, Planned order Receipt for period t = 0

iii) On hand at end of period t = 0 ( when On hand inventory at beginning of period t < Gross requirement for period t)

In such case ,

Planned order receipt for period t > Gross requirement for period t – On hand inventory at beginning of period t

iv) Since Lead time is 1 week ,

Planned order receipt for period t = Planned order Release for period t-1

Given are :

Holding cost = $2.50 per unit per week

Set up cost = $ 200 ( We presume set up cost is incurred EVERYTIME AN ORDER IS RELEASED)

Total quantity of inventory held for 1 week = 20 + 20 = 40

Therefore ,

Holding cost = $ 2.50 x 40 = $100

Total number of Planned Order Releases = 7

Therefore ,

Total Set up Cost = $200 / set up x 7 ( number of set ups ) = $1400

Thus total relevant cost

= Total inventory holding cost + Total set up cost

= $100 + $ 1400

= $ 1500

TOTAL RELEVANT COST FOR GROSS REQUIREMENTS = $1500

Beginning inventory : 40

                                                              Week

Lot size: Lot for Lot

Lead time: 1 week

1

2

3

4

5

6

7

8

9

10

11

12

Gross Requirement

20

0

40

0

40

70

30

0

10

80

0

50

On hand at beginning of period : 40

40

20

20

0

0

0

0

0

0

0

0

0

On hand at end of period

20

20

0

0

0

0

0

0

0

0

0

0

Planned order receipt

0

0

20

0

40

70

30

0

10

80

0

50

Planned order release

0

20

0

40

70

30

0

10

80

0

50

0