please explain each step! thanks :) 5. Building a bookstore consists of six majo
ID: 368327 • Letter: P
Question
please explain each step! thanks :)
Explanation / Answer
Expected duration of activity E
=( 2 + 4 X 3 + 7 )/6
= 3.5 days
Standard deviation of activity E = ( 7 -2 )/6 = 5/6
Hence, Variance of activity E = ( 5/6)^2 = 25/36 = 0.694
EXPECTED DURATION OF ACTIVITY E = 3.5 DAYS
VARIANCE OF ACTIVITY E = 0.694
The parallel paths and their corresponding cumulative expected durations as follows :
A-C-E-F = 4 + 6 + 3.5 + 8 = 21.5 days
A-C-F = 4 + 6 + 8 = 18 days
B-D-F = 5 + 10 + 8 = 23 days
B-C-F = 5 + 6+ 8 = 19 days
B-C-E-F = 5 +6 + 3.5 + 8 = 22.5 days
Since B-D-F has the longest expected duration, it forms the critical path
CRITICAL ACTIVITIES ARE = B, D and F
EXPECTED TIME TO COMPLETE THE PROJECT = 23 DAYS
Variance of the critical path
= Variance of B + Variance of D + Variance of F
= 0.5 + 0.3 + 0.2
= 1
Hence, Standard deviation of the critical path = Square root ( Variance ) = 1
Let Z value corresponding to the probability that the project will complete in max 25 days = Z1
Therefore ,
Expected duration of critical path + Z x Standard deviation of critical path = 25
Or, 23 + Z = 25
Or, Z = 2
Hence corresponding Probability for Z = 2 as derived from standard normal distribution table
= 0.97725
Therefore,
Probability that the project will be completed in maximum 25 days = 0.97725
Hence,
Probability that the project will be completed in 25 or more days
= 1 – Probability that the project will be completed in maximum 25 days
= 1 – 0.97725
= 0.02275
PROBABILITY THAT THE PROJECT IS COMPLETED IN MAXIMUM 25 OR MORE DAYS = 0.02275
EXPECTED DURATION OF ACTIVITY E = 3.5 DAYS
VARIANCE OF ACTIVITY E = 0.694
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.