If 23 units of the end item are to be assembled, how many additional units of E
ID: 366902 • Letter: I
Question
If 23 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)
An order for the end item is scheduled to be shipped at the start of week 15. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)
Explanation / Answer
a)
Following formula are used to calculate the net requirement
Net requirement = Gross requirement - Amount on hand
Gross requirement = Net requirement of parent item * usage factor
Net requirement of End item = Gross requirement - Amount on hand = 23 - 0 = 23
Gross requirement of B = Net requirement of End item * Usage = 23*2 = 46
Net requirement of B = Gross requirement - Amount on hand = 46 - 10 = 36
Net requirement of C = Net requirement of End item * Usage - Amount on hand = 23*1 - 10 = 13
Net requirement of D = Net requirement of End item * Usage - Amount on hand = 23*3 - 25 = 44
Net requirement of E = Net requirement of B*Usage factor + Net requirement of C*Usage factor + Net requirement of D*Usage factor - Amount on hand = 36*2+13*2+44*2-12 = 174
Additional units = 174
b)
The longest lead time is required by End item + D + H = 1+3+2 = 6 weeks
Therefore, for order to be shipped at the start of week 15, it has to be started 6 weeks in advance, i.e. at the start of week 9
The latest week = 9
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.