MS.51 An office furniture manufacturer needs to calculate material requirements for one of its most popular office chairs. The graphic above shows the bill of material for this item. Below is the MRP table for the top-level assembly (the chair):
Based on the information in the "Chair" table above, what are the Net Requirementsin the week of 8/15?
What are the Planned Order Releases in the week of 9/5?
What are the Scheduled Receipts in the week of 9/19?
What is the Projected On-Hand Inventory quantity in the week of 9/26?
Chair Final Assembly 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 Gross Requirements 300 300 400 400 400 400 400 500 300 Scheduled Receipts 120 480 480 Projected On-Hand Inv. 310 Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) 1 Lot Size 120 Bill of Material for Chair Chair Final Assembly Base Assembly (1 required) (other parts...) Caster (other parts...) (5 required)Explanation / Answer
the MRP schedule is as follows
week
8/1
8/8
8/15
8/22
8/29
9/5
9/12
9/19
9/26
GR
300
300
400
400
400
400
400
500
300
SR
120
480
480
POH (ending inv)
310
0+310+ 120-300
= 130
240+130 +0-300
= 70
30
110
70
150
110
90
30
NR
0
300-130
= 170
330
290
250
390
210
PORp
0
240
360
360
360
480
240
PORs
240
360
360
360
480
240
NR in week of 8/15 = 330
PORs in the week 9/5 = 360
SR in week 9/19 = 0
POH in week 9/26 = 30
week
8/1
8/8
8/15
8/22
8/29
9/5
9/12
9/19
9/26
GR
300
300
400
400
400
400
400
500
300
SR
120
480
480
POH (ending inv)
310
0+310+ 120-300
= 130
240+130 +0-300
= 70
30
110
70
150
110
90
30
NR
0
300-130
= 170
330
290
250
390
210
PORp
0
240
360
360
360
480
240
PORs
240
360
360
360
480
240