DQuestion 12 1 pts One week into the project, you run into a snag with two of th

ID: 366176 • Letter: D

Question

DQuestion 12 1 pts One week into the project, you run into a snag with two of the project suppliers. The company installing the fuel tank encountered some faulty materials which will add 3 weeks to that installation activity. The company conducting the communication checks will take 4 weeks rather than the projected 3 weeks. If you hold an insurance policy that will pay $50,000 for every week the project is delayed over the overall project length, how much insurance money can you expect to collect? $150,000 $200,000 $0 $50,000 $100,000

Explanation / Answer

the project is delayed by total of 4 weeks, 3 weeks installation and 1 week communication check. So, insurance money that can be expected to recover is - 50000*4 = 200000