Homework: HW12 Score: 0 of 25 pts Problem 3.32 8018(0com plete) HW Score: 0%, 0 of 100 pts Question Help * Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens The activities necessary to build an experimental model and related data are listed in the following table: Total Cost Normal Time Crash Time Norma with (weeks) (weeks) Cost Crashing Immediate $1,400 $2,100 $2,000 $2,800 $350 $1,400 $1,720 $850 $1,150 $4,000 $5,000 $1,800 $2.400 $350 D. E a) Based on the given information regarding the activities for the project, the project completion date weeks.Explanation / Answer
the given network completion period is 14 weeks
the critical path of this network is - A-D-G
the durations of each actitity is= 3+7+4= 14 weeks,
the remaining paths carrying less time than 14 weeks, hence the project can be completes in 14 weeks.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.