ezto.mheducation.com/hm.tpx Problem 12-14 Using the diagram below, do the follow

ID: 365444 • Letter: E

Question

ezto.mheducation.com/hm.tpx Problem 12-14 Using the diagram below, do the following: Prepare an MRP for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on Day 6. Note There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand. (Leave no cells blank - be certain to enter "O" wherever required.) Bent plastic grip Straight ade Top Bent blade Bottom traight plastic grip Beg Inv

Explanation / Answer

MRP for scissors

Part

Lead Times (week)

Beg Inv

reqd

Scissors

1

0

600 pcs on day 6

Bottom Blade Assembly

1

0

Top Blade Assembly

1

40

Screw

1

0

Straight Blade

1

200

Straight Plastic Grip

2

0

Bent Blade

1

350

Bent Plastic Grip

2

0

Scissors (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

0

0

600

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

0

0

600

Planned Order Receipts

0

0

0

0

0

0

600

Planned Order Releases

0

0

0

0

0

600

0

Bottom Blade Assembly (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

0

600

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

0

600

0

Planned Order Receipts

0

0

0

0

0

600

0

Planned Order Releases

0

0

0

0

600

0

0

Top Blade Assembly (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

0

600

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

40

40

40

40

40

40

0

Net Requirements

0

0

0

0

0

560

0

Planned Order Receipts

0

0

0

0

0

560

0

Planned Order Releases

0

0

0

0

560

0

0

Screw (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

0

600

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

0

600

0

Planned Order Receipts

0

0

0

0

0

600

0

Planned Order Releases

0

0

0

0

600

0

0

Straight Blade (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

600

0

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

200

200

200

200

200

0

0

Net Requirements

0

0

0

0

400

0

0

Planned Order Receipts

0

0

0

0

400

0

0

Planned Order Releases

0

0

0

400

0

0

0

Straight Plastic Grip (LT=2 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

600

0

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

600

0

0

Planned Order Receipts

0

0

0

0

600

0

0

Planned Order Releases

0

0

600

0

0

0

0

Bent Blade (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

560

0

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

350

350

350

350

350

0

0

Net Requirements

0

0

0

0

210

0

0

Planned Order Receipts

0

0

0

0

210

0

0

Planned Order Releases

0

0

0

210

0

0

0

Bent Plastic Grip (LT=2 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

560

0

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

560

0

0

Planned Order Receipts

0

0

0

0

560

0

0

Planned Order Releases

0

0

560

0

0

0

0

Note:

GR of Bottom Blade Assembly = POR of Scissors

GR of Top Blade Assembly = POR of Scissors

GR of Screw = POR of Scissors

GR of Straight Blade = POR of Bottom Blade Assembly

GR of Straight Plastic Grip = POR of Bottom Blade Assembly

GR of bent Blade = POR of top Blade Assembly

GR of bent Plastic Grip = POR of top Blade Assembly

GR: Gross Requirements

POR: Planned Order Release

Net Requirements = GR-scheduled reciepts-on hand

planned order receipts = net requirements

MRP for scissors

Part

Lead Times (week)

Beg Inv

reqd

Scissors

1

0

600 pcs on day 6

Bottom Blade Assembly

1

0

Top Blade Assembly

1

40

Screw

1

0

Straight Blade

1

200

Straight Plastic Grip

2

0

Bent Blade

1

350

Bent Plastic Grip

2

0

Scissors (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

0

0

600

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

0

0

600

Planned Order Receipts

0

0

0

0

0

0

600

Planned Order Releases

0

0

0

0

0

600

0

Bottom Blade Assembly (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

0

600

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

0

600

0

Planned Order Receipts

0

0

0

0

0

600

0

Planned Order Releases

0

0

0

0

600

0

0

Top Blade Assembly (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

0

600

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

40

40

40

40

40

40

0

Net Requirements

0

0

0

0

0

560

0

Planned Order Receipts

0

0

0

0

0

560

0

Planned Order Releases

0

0

0

0

560

0

0

Screw (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

0

600

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

0

600

0

Planned Order Receipts

0

0

0

0

0

600

0

Planned Order Releases

0

0

0

0

600

0

0

Straight Blade (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

600

0

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

200

200

200

200

200

0

0

Net Requirements

0

0

0

0

400

0

0

Planned Order Receipts

0

0

0

0

400

0

0

Planned Order Releases

0

0

0

400

0

0

0

Straight Plastic Grip (LT=2 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

600

0

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

600

0

0

Planned Order Receipts

0

0

0

0

600

0

0

Planned Order Releases

0

0

600

0

0

0

0

Bent Blade (LT=1 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

560

0

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

350

350

350

350

350

0

0

Net Requirements

0

0

0

0

210

0

0

Planned Order Receipts

0

0

0

0

210

0

0

Planned Order Releases

0

0

0

210

0

0

0

Bent Plastic Grip (LT=2 week)

Beg Inv

1

2

3

4

5

6

Gross Requirements

0

0

0

0

560

0

0

Scheduled Receipts

0

0

0

0

0

0

0

On Hand

0

0

0

0

0

0

0

Net Requirements

0

0

0

0

560

0

0

Planned Order Receipts

0

0

0

0

560

0

0

Planned Order Releases

0

0

560

0

0

0

0

Note:

GR of Bottom Blade Assembly = POR of Scissors

GR of Top Blade Assembly = POR of Scissors

GR of Screw = POR of Scissors

GR of Straight Blade = POR of Bottom Blade Assembly

GR of Straight Plastic Grip = POR of Bottom Blade Assembly

GR of bent Blade = POR of top Blade Assembly

GR of bent Plastic Grip = POR of top Blade Assembly

GR: Gross Requirements

POR: Planned Order Release

Net Requirements = GR-scheduled reciepts-on hand

planned order receipts = net requirements