Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

2) The company decided that the project in the previous problem has to be expedi

ID: 363320 • Letter: 2

Question

2) The company decided that the project in the previous problem has to be expedited in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting the project reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below.

Activity

Normal

Time

(days)

Expedited

Time

(days)

Normal

Cost

($)

Expedited

Cost

($)

A

32

26

200

500

B

21

20

300

375

C

30

30

200

200

D

45

40

200

800

E

26

20

700

1,360

F

28

24

1,000

1,160

G

20

18

400

550

From this table you can compute the direct cost incurred by expediting an activity by one day.

Answer the following questions:

2.1) (25 points) What is the optimal time to complete the project?

2.2) (25 points) What is the optimal project cost?

Activity

Normal

Time

(days)

Expedited

Time

(days)

Normal

Cost

($)

Expedited

Cost

($)

A

32

26

200

500

B

21

20

300

375

C

30

30

200

200

D

45

40

200

800

E

26

20

700

1,360

F

28

24

1,000

1,160

G

20

18

400

550

Explanation / Answer

The optimal time to complete the project is 73 days. Consider the following information:

Activity Normal Time (days) Expedited Time (days) Normal Cost ($) Expedited Cost ($) Cost/ day ($)
A 32 26 200 500 50
B 21 20 300 375 75
C 30 30 200 200 -
D 45 40 200 800 120
E 26 20 700 1,360 110
F 28 24 1,000 1,160 40
G 20 18 400 550 75

Cost/day = (Expedited Cost – Normal Cost)/(Normal Time – Expedited Time)
Critical path : AEG : duration = 78

CFG : duration = 78

The company shoudl expedite activity G by 1 day, then the duration becomes 77 days and $75 is added to the total cost of the project. This also adds A-D as a critical path. Next expedite A & E by 2 days each, so the completion time now is 73 days while adding an additional cost of $ 90 per day to the total cost of the project.

The optimal project cost is $ 75 + 90 + 187.5+ 646.15+ 380= $1378.65

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote