The demand for subassembly S is 110 units in week 7. Each unit of S requires 1 u
ID: 363311 • Letter: T
Question
The demand for subassembly S is 110 units in week 7. Each unit of S requires 1 unit of T and 2 unitss of U. Each unit of T requires 1 unitnothing of V, 1 unitnothing of W, and 1 unit of X. Finally, each unit of U requires 2 unitss of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 weeknothing to make T, 2 weeks to make U, 2 weekss to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers).
Calculate S-Z's Gross req, on hand, net req, order receipt and order release mathxl.com Homework: Chapter 13 and Chapter 14 Homeworlk My Score: 37.03%, 37-03 of 100 pts Question Help * each unit of U requires 2 units ofy Score: 0.38 of 5 pts 14 of 20 (11 complete) Problem 14.7 damand for subassembly S is 110 units in wook 7.Each unit of S requires 1 unt of T and 2 units of U. Each unit of T roquires 1 unit of V.1 un of W, and 1 3 units of Z One firm manufactures all items. It takes 2 weeks to make s, 1 week to make T, 2 weeks to make U, 2 weoks to make V, 3 1 unit of W, and 1 unit of X. Finally, weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 woek to make Z cek 'ho ion b view the product structure ard the time-phased product structur Click the icon b view the on-hand mentary. Construct a net material requirements plan using on-hand invenitory fenter your responsss as whole numbera). Lead Time 1 2 3 4 5 6 7 (weeka) Order receipt More Info X More Into The product structure. The time-phased product structure On-Hand On-Hand Inventory tem Inventory 20 20 30 20 30 25 300 40 Level Print Done Time in weaks Print Done r your anower in the edit fields and then click Check AnswerExplanation / Answer
Based on the Information provided in the question, we can draw the material requirement plan as below:
Product Item S Order Policy L4L Lead Time 2 Week 1 2 3 4 5 6 7 Gross Requirement 0 0 0 110 Scheduled 0 0 0 0 0 0 0 Opening Inventory 20 20 20 20 20 20 20 Closing Inventory 20 20 20 20 20 20 0 Requirement 0 0 0 90 Planned Order receipt 0 0 0 90 Planned Order Released 0 0 0 90 0 0 Safety Stock 0 0 0 0 0 0 0 Product Item T Order Policy L4L Lead Time 1 Week 1 2 3 4 5 6 7 Gross Requirement 0 90 0 0 Scheduled 0 0 0 0 0 0 0 Opening Inventory 20 20 20 20 20 0 0 Closing Inventory 20 20 20 20 0 0 0 Requirement 0 70 0 0 Planned Order receipt 0 70 0 0 Planned Order Released 0 0 70 0 0 0 Safety Stock 0 0 0 0 0 0 0 Product Item U Order Policy L4L Lead Time 2 Week 1 2 3 4 5 6 7 Gross Requirement 0 180 0 0 Scheduled 0 0 0 0 0 0 0 Opening Inventory 30 30 30 30 30 0 0 Closing Inventory 30 30 30 30 0 0 0 Requirement 0 150 0 0 Planned Order receipt 0 150 0 0 Planned Order Released 0 150 0 0 0 0 Safety Stock 0 0 0 0 0 0 0 Product Item V Order Policy L4L Lead Time 2 Week 1 2 3 4 5 6 7 Gross Requirement 0 70 0 0 Scheduled 0 0 0 0 0 0 0 Opening Inventory 20 20 20 20 20 0 0 Closing Inventory 20 20 20 0 0 0 0 Requirement 0 50 0 0 Planned Order receipt 0 50 0 0 Planned Order Released 0 50 0 0 0 0 Safety Stock 0 0 0 0 0 0 0 Product Item W Order Policy L4L Lead Time 3 Week 1 2 3 4 5 6 7 Gross Requirement 0 0 70 0 0 Scheduled 0 0 0 0 0 0 0 Opening Inventory 30 30 30 30 30 0 0 Requirement 0 0 0 40 0 0 Planned Order receipt 0 40 0 0 Planned Order Released 40 0 0 0 0 0 Safety Stock 0 0 0 0 0 0 0 Product Item X Order Policy L4L Lead Time 1 Week 1 2 3 4 5 6 7 Gross Requirement 0 70 0 0 Scheduled 0 0 0 0 0 0 0 Opening Inventory 25 25 25 25 25 0 0 Closing Inventory 25 25 25 25 0 0 0 Requirement 0 45 0 0 Planned Order receipt 0 45 0 0 Planned Order Released 0 0 45 0 0 0 Safety Stock 0 0 0 0 0 0 0 Product Item Y Order Policy L4L Lead Time 2 Week 1 2 3 4 5 6 7 Gross Requirement 0 0 300 0 0 Scheduled 0 0 0 0 0 0 0 Opening Inventory 300 300 300 300 300 0 0 Closing Inventory 300 300 300 300 0 0 0 Requirement 0 0 0 0 Planned Order receipt 0 0 0 0 Planned Order Released 0 0 0 0 0 0 Safety Stock 0 0 0 0 0 0 0 Product Item Z Order Policy L4L Lead Time 1 Week 1 2 3 4 5 6 7 Gross Requirement 0 450 0 0 Scheduled 0 0 0 0 0 0 0 Opening Inventory 40 40 40 40 40 0 0 Closing Inventory 40 40 40 40 0 0 0 Requirement 0 410 0 0 Planned Order receipt 0 410 0 0 Planned Order Released 0 0 410 0 0 0 Safety Stock 0 0 0 0 0 0 0Related Questions