Guidelines for Assignment: Before going into the assignment, it will be good ify
ID: 3612216 • Letter: G
Question
Guidelines for Assignment:
Before going into the assignment, it will be good ifyou go through the following key points.
COCOMO Models
1. Basic Model
2. Intermediate Model
3. Detail Model
Given below are the formulae for effort estimation for BASICVersion’s modes.
Organic:
E = 3.2 x (size in KLOC)1.05
Semi Detached:
E = 3.0 x (size in KLOC)1.12
Embedded :
E = 2.8 x(size in KLOC)1.20
Given below are the formulae to calculate the Time required forproject schedule.
Organic:
T = 2.5 x (Effort).38
Semi Detached:
T = 2.5 x (Effort).35
Embedded :
T = 2.5 x( Effort).32
Formula to calculate the number of people is...
Total number of people needed= Effort / Total time todevelop
Given below are the formulae for effort estimation forIntermediate Version’s modes.
Organic:
E =EAF*3.2*(KLOC)1.05
Semi Detached:
E = EAF*3.0 x (KLOC)1.12
Embedded :
E = EAF*2.8 x( KLOC)1.20
Given below are the formulae to calculate the Time required forproject schedule.
Organic:
T = 2.5 x (Effort).38
Semi Detached:
T = 2.5 x (Effort).35
Embedded :
T = 2.5 x( Effort).32
Assignment Questions
Q#1: Your team is asked to develop criticalsoftware of health insurance system, as the project is complex andsensitive related to the Insurance of health so there is no chanceof error. If the size of the project is 33200LOC then calculate the“Effort” in person month, and“Time” required to develop (Schedule)the Software in months, with the number of people required tocomplete the project using “Organic DevelopmentMode”. [15]
Q#2: Write down the characteristics of highquality WBS. [10]
Q#3: Draw the figure about when the preparationof the SRS document can begin.[5]
Organic:
E = 3.2 x (size in KLOC)1.05
Semi Detached:
E = 3.0 x (size in KLOC)1.12
Embedded :
E = 2.8 x(size in KLOC)1.20
Explanation / Answer
Dear User, EffortEstimation for organic Mode(E) = 3.2 *(33200)1.05 = 178790.72 Time requiredfor project schedule in Organic Mode(T) = 2.5 * (178790.72)^0.38= 2.5 * 99.5835 =247.645 months Thenumber of people required to complete the project using OrganicDevelopment Mode = Effort Estimation / Total time to develop = 178790.72/247.645 = 721.96 = 722 people I hope this will helps toyou EffortEstimation for organic Mode(E) = 3.2 *(33200)1.05 = 178790.72 Time requiredfor project schedule in Organic Mode(T) = 2.5 * (178790.72)^0.38
= 2.5 * 99.5835 =247.645 months Thenumber of people required to complete the project using OrganicDevelopment Mode = Effort Estimation / Total time to develop = 178790.72/247.645 = 721.96 = 722 people I hope this will helps toyou