2. The production planning and control department (PPCD) at VECO Metal is going
ID: 361004 • Letter: 2
Question
2. The production planning and control department (PPCD) at VECO Metal is going to analyze and improve a production line with two single-machine stations (i.e. A & B). PPCD made the assumption of exponential distribution for both arrival rate and processing time. PPCD also recorded new values for arrival rate and average (effective) processing time for stations A and B as follows Station Arrival rate (parts/day) Processing time (hour) 0.95 0.90 a) Determine if the parts spend more time in station A or B (in average). b) What is the average number of jobs at station A? c) At station B, what happens to CT and WIP if the arrival rate (parts/hour) approaches the value of process rate?Explanation / Answer
a)
System A
Arrival rate, 1 = 6
Processing rate, 1 = 8/0.95 = 8.42 (assuming 8 hours a day)
Average time in station A = 1/(1 - 1) = 1/(8.42 - 6) = 0.413 day = 3.31 hours
System B
Arrival rate, 2 = 7
Processing rate, 2 = 8/0.90 = 8.9 (assuming 8 hours a day)
Average time in station B = 1/(2 - 2) = 1/(8.9 - 7) = 0.529 day = 4.24 hours
Parts spend more time in station B
b) Average number of jobs at station A = 1/(1 - 1) = 6/(8.42 - 6) = 2.48
c) If arrival rate approaches processing rate, the CT and WIP become very large.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.