2:03 PM moodle.selu.edu oo AT&T; 9 of 11 9. For the network shown below with all times indicating weeks, answer the following questions a) b) c) d) What is the impact on the end date of the project if activity B slips by two wecks? What is the impact on the end date of the project if activity E slips by one week? What is the impact on the end date of the project if activity D slips by two wecks? If the customer offered you bonus for completing the project in sixteen wecks or less, which activities would you focus on first as part of crashing (compression) analyses? START FINISH

Explanation / Answer

a.No impact on schedule as B's output is required in 12th week
b. E slips by one week means project slips by a week
c.D slips by 2 weeks, no slippage in project. D gets finished by 15the
week where as E finishes by 18th week so D has 3 week margin.
d. If compression happens it has to happen on the critical path.So in this
   case activities to be considered as A,C and E