Assume you have completed three months of the project. The budget at completion
ID: 3574737 • Letter: A
Question
Assume you have completed three months of the project. The budget at completion (BAC) was $200 000 for this six month project. Also assume the following:
Planned value (PV) =$120,000
Earned value (EV) =$100,000
Actual cost (AC) = $90,000
a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b). How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
c). Use the cost performance (CPI) to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
Explanation / Answer
given detaila are Planned value (PV)=$120,000
Earned value (EV)=$100,000
Actusl cost (AC)=$90,000
a) The cost variance (CV)= EV-AC
=$100,000-$90,000
=$ 10000
Schedule variance =EV-PV
=$100,000-$120000
=$-20000
Cost perfomance index (CPI) = (EV)/(AC)
=($100,000)/($90,000)
=1.11111
Schedule perfomance index (SPI) =(EV)/(PV)
=($100,000)/($120,000)
=0.833
b) Since the schedule perfomance index (SPI) is less than one little amount of work is finished than the planned work.otherwise the project is behind schedule.
and also since the cost perfomance index(CPI) is greater than one the project is under budget.
c) Estimate at completion (EAC) = BAC/CPI
=200,000/1.1111111
=180000
Therefore the project perfomance is worse than the project.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.