In the lecture we discussed the supply chain decision phases as falling into a m
ID: 355236 • Letter: I
Question
In the lecture we discussed the supply chain decision phases as falling into a matrix, comprising the categories Procurement, Production, Distribution and Sales, and into the time frames long-term, mid-term, and short-term.
A semiconductor firm has to decide how much of its production it can produce using its in-house facilities and how much it will need to off-load to subcontractors for the next 4 to 18 months.
Where does this decision fall in the supply chain decision phase matrix?
Select one:
a. Long-term and Procurement
b. Long-term and Production
c. Mid-term and Production
d. Mid-term and Distribution
Explanation / Answer
Answer: This falls under (c) Mid Term and production. The period of 4-18 months is a midterm time frame period and the category which this decision falls comes under the production decision and hence Mid Term and production is the right answer.