Rockness Recycling refurbishes rundown business students. The process uses a mov

ID: 352909 • Letter: R

Question

Rockness Recycling refurbishes rundown business students. The process uses a moving belt, which carries each student through the five steps of the process in sequence. The five steps are as follows: 2. Time required per student (minutes) Step Description 1 Unpack and place on bet 2.5 0.8 2Strip off bad habits 4 5 Polish and pack Scrub and clean mind Insert modern method 1.2 One faculty member is assigned to each of these steps. Faculty members work a 37.5- hour week and rotate jobs each week. What is the maximum number of students that Rockness Recycling can refurbish per week?

Explanation / Answer

The process is divided into 5 steps, however, the maximum number of students that Rockness Recycling can refurbish will depend on the slowest step of the process which would govern the whole process

In our case the Slowest step is Step 2 "Strip of Bad habits" and the number of students can be calculated as below

Output = Available Time / Cycle time

Output = (37.5 hour work week * 60 minute per hour) / (2.5 minute cycle time)

Output = (37.5 * 60) / 2.5 = 900 students

So the maximum students it can Refurbish are 900 students