1. Xavier and Yvette have been paired up to analyze the needs of ZZZ Sleepers ma

ID: 352390 • Letter: 1

Question

1. Xavier and Yvette have been paired up to analyze the needs of ZZZ Sleepers mattress stuffers. ZZZ is experiencing a negative market impact from all the mattresses with air inside. They want to either improve their product or lay off half of their mattress stuffers. Xavier has experience analyzing the needs of project rollouts. Yvette has experience in analyzing the needs of employee development projects. This situation may be neither a rollout nor a development need. What kind of project is this? What strengths will each of these individuals bring to that type of project (besides experience doing other performance analyzes)? Where are they likely to be “in conflict” with each other’s methods? (Note: this question is really about defining the focus of an analysis, the stages of analysis and the probable differences in types of skills that someone specializing in one situation will have.)

Explanation / Answer

What kind of project is this?

In this kind of project the company is not sure about what to do. They are either looking at changing product or to layoff people in order to save costs . So here they are inviting people with different skills and competencies to guide them to a decision.

What strengths will each of these individuals bring to that type of project (besides experience doing other performance analyzes)?

Xavier can look into the issue from the point of view of initialising a new project while Yvette will look into the perspective of talent management and human competencies. These people can complement each other and may lead to superior results. Yvette can understand the employee needs making the organization see what their employees are lacking and thus instead of layoff she can plan new skill development or external hiring. while xavier can say that the new product need to be developed as per following guidelines and hence can guide into how to set up project planning

Where are they likely to be “in conflict” with each other’s methods?

They will most likely to be in conflict regarding end stage or recommendations of each other's methods. One is focussed on process the other on humans. Also final recommendations would be starkingly dissimar and both can make convincing arguments to support each case