Which of the following plans has the longest planning horizon and the least level of detail?

a. aggregate production plan

b. material requirements planning

c. master production schedule

d. all of the above have the same level of detail

. none of the above

In terms of INCREASING level of detail, which is the best sequence of activities?

I. Material requirements planning.

II. Master production scheduling.

III. Aggregate production planning.

a. I, II and III

b. I, III, and II

c. II, III, and I

d. II, I, and III

e. III, II, and I

Explanation / Answer

a) Aggregate production plan has the longest planning horizon and the least level of detail

It has the longest planning origin from 6 to 18 months and provide details related to forecast, current inventory and production output etc.

b) In terms of increasing level of detail, the best sequence of activities is -

e) III, II and I

Aggregate Planning has lowest level of detail, MPS has the next level detail and MRP has highest level of detail with component requirements.