ch. 9110 Time Cost Time Cost r Immediate Predecessors Activity $3,000 7,000 3 $4
ID: 351343 • Letter: C
Question
ch. 9110 Time Cost Time Cost r Immediate Predecessors Activity $3,000 7,000 3 $4,000 2 4,600 5 $15,000 5 $15,000 5 2 $3,000 1 s 3,500 A,B,C C,D 2 $1,500 1 S 2,400 4 $4,0001 7,000 5 $7,000 4 $12,000 7 $8,000 5 $20,000 D, F Write the objective function and constraints to crash the above project to 14 units of time. Show work for any calculations and show work using algebra to change constraints, as needed, so all variables are on one side of each constraint. Do not solve. Do not identify the variablesExplanation / Answer
Determine allowable crashing limit for each activity and Crashing cost per period for each activity.
Activity
Predecessors
Normal Time (days)
Crash time (days)
Normal Cost
Crash cost
Allowable Crashing Limit
Crashing Cost per period
A
Start
5
1
3000
7000
4
1000
B
Start
3
2
4000
4600
1
600
C
Start
5
5
15000
15000
0
0
D
A, B, C
2
1
3000
3500
1
500
E
C, D
2
1
1500
2400
1
900
F
A
4
1
4000
7000
3
1000
G
D, F
5
4
7000
12000
1
5000
H
E
7
5
8000
20000
2
6000
LPP formulation
Let,
Xi = Finish time for activity i
Yi = amount of time activity i is crashed
Every activity should satisfy the relationship between finish time, earliest start time, and activity time as follows:
Finish time >= Earliest time + Activity Time = Earliest time + (Normal time – Crashed amount)
Activity
Comment
Equation
A
Starting activity
XA >= 0 + (5 – YA)
XA + YA >= 5
B
Starting activity
XB >= 0 + (3 – YB)
XB + YB >= 3
C
Starting activity
XC >= 0 + (5 – YC)
XC + YC >= 5
D
A is predecs.
XD >= XA + (2 – YD)
XD - XA + YD >= 2
D
B is predecs.
XD >= XB + (2 – YD)
XD – XB + YD >= 2
D
C is predecs.
XD >= XC + (2 – YD)
XD – XC + YD >= 2
E
C is predecs.
XE >= XC + (2 – YE)
XE – XC + YE >= 2
E
D is predecs.
XE >= XD + (2 – YE)
XE – XD + YE >= 2
F
A is predecs.
XF >= XA + (4 – YF)
XF – XA + YF >= 4
G
D is predecs.
XG >= XD + (5 – YG)
XG – XD + YG >= 5
G
F is predecs.
XG >= XF + (5 – YG)
XG – XF + YG >= 5
H
E is predecs.
XH >= XE + (7 – YH)
XH – XE + YH >= 7
Project has to be completed within 14 UNITS (G and H are finishing activities)
XG <= 14
XH <= 14
Maximum allowable crashing time for each activity
YA <= 4,
YB <= 1,
YC <= 0,
YD <= 1,
YE <= 1,
YF <= 3,
YG <= 1,
YH <= 2,
Non-negative constraint
All Xi and Yi >= 0
Activity
Predecessors
Normal Time (days)
Crash time (days)
Normal Cost
Crash cost
Allowable Crashing Limit
Crashing Cost per period
A
Start
5
1
3000
7000
4
1000
B
Start
3
2
4000
4600
1
600
C
Start
5
5
15000
15000
0
0
D
A, B, C
2
1
3000
3500
1
500
E
C, D
2
1
1500
2400
1
900
F
A
4
1
4000
7000
3
1000
G
D, F
5
4
7000
12000
1
5000
H
E
7
5
8000
20000
2
6000