Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

courses/7735/quizzes/28816/take Question3 2 pts If three workers are assigned to

ID: 351244 • Letter: C

Question

courses/7735/quizzes/28816/take Question3 2 pts If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days. The tasks can be completed independently of each other. If you are to schedule with a resource-limit, what is the minimum resource limit for the project? Three workers per day e 21 worker-days Seven days Additional information is needed to determine the minimum number. Question 4 2 pts

Explanation / Answer

Every day he needs maximum of 3 workers, so this can be set of the minimum resource limit for the project.

A: Three workers per day