C&A Furniture uses a four-step process to make its famous wood table: Process Pr
ID: 350371 • Letter: C
Question
C&A Furniture uses a four-step process to make its famous wood table:
Process
Processing Time (minutes)
Milling—table top
10
Milling—table stand
5
Assembly
15
Finishing
20
The milling machine requires a setup time of 30 minutes to make table tops and a changeover time of 30 minutes to make table stands.C&A works an 8-hour day.What is the capacity of the milling machine (in tables per day) if the batch size is 10?
O0.05
O6.40
O22.86
OCannot be determined
Process
Processing Time (minutes)
Milling—table top
10
Milling—table stand
5
Assembly
15
Finishing
20
Explanation / Answer
Capacity of the milling machine (in tables per day) with batch size of 10 is 22.86
Batch size: 10
Time: (Time for table tops) + (Time for table stands)
: (Setup time + processing time for table tops) + (Setup time + processing time for table stands)
: (30+10*10)+(30+10*5)
: 210 mins
Capacity in day = (# of units/Time for table machine)*(duration in day)
= (10/210)*(8*60)
= 22.86 units/day