Jessica hires ChromaLite Builders Corp. to construct a house. The contract speci
ID: 349866 • Letter: J
Question
Jessica hires ChromaLite Builders Corp. to construct a house. The contract specifies that grade A+ carpeting is to be installed on the entire second floor. ChromaLite Builders accidentally installs grade A carpeting instead. Few people, except for carpeting experts, can tell the difference. Jessica, however, refuses to pay for the construction citing that ChromaLite Builders has breached the contract. Which of the following statements is true in this scenario?
Daniel’s failure to deliver ice-cream makers and waffle makers on time resulted in a two-week delay in the opening of Sheena’s new ice-cream parlor. Sheena incurred a heavy loss since she had to pay the rent for those two weeks as well as salaries to the personnel she had hired. In her contract for the delivery, she specified that time was of the essence and that the delivery of the ice-cream and waffle makers was critical to the business. In this case, which of the following remedies is a court most likely to award Sheena?
The courts are likely to consider ChromaLite Builders’s performance as a substantial performance, and Jessica will have to pay something but not the full amount; i.e. she is entitled to monetary damagesExplanation / Answer
Answer:- Jessica hires ChromaLite Builders Corp. to construct a house. The contract specifies that grade A+ carpeting is to be installed on the entire second floor. ChromaLite Builders accidentally installs grade A carpeting instead. Few people, except for carpeting experts, can tell the difference. Jessica, however, refuses to pay for the construction citing that ChromaLite Builders has breached the contract. Which of the following statements is true in this scenario?
Correct Answer:-
The court is likely to declare that Bob's has breached the contract, and will ask Jessica to pay half cost decided as per the contract.
Explanation:
This is because the contract between Jessica stated clearly that Bob's should install grade A+ hence the installation of grade A and not grade A+ is a breach of the contract thus Bob's will be liable by receiving a half pay as per the contract.
Answer:- Daniel’s failure to deliver ice-cream makers and waffle makers on time resulted in a two-week delay in the opening of Sheena’s new ice-cream parlor. Sheena incurred a heavy loss since she had to pay the rent for those two weeks as well as salaries to the personnel she had hired. In her contract for the delivery, she specified that time was of the essence and that the delivery of the ice-cream and waffle makers was critical to the business. In this case, which of the following remedies is a court most likely to award Sheena?
Correct Answer:- Consequential Damages.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.