Super Fun Industries manufactures four top-selling toys code named A-148, B-356,
ID: 3496514 • Letter: S
Question
Super Fun Industries manufactures four top-selling toys code named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 18 hours a day, 5 days a week, and 4 hours on Saturday Processing Time Station 1 Processing Time Station 2 Processing Time Station 3 Processing Time Station 4 A-148 6 min 4 min B-356 7 min 1 min B-457 0 min 5 min 2 min 10 min C-843 9 min min 0 min 4 min min If weekly demand for the four products are A 148-30 units, B 356 = 430 units, B 457s 240 units, and C 843-160 units, which station is the bottleneck, and is t capable of producing all the toys demanded? with a utilization of»% (Enter your response rounded to one decimal place ) The bottleneck for Super Fun Industries isExplanation / Answer
The bottleneck for Super Fun Industries is Station 1. It is capable of producing all the toys demanded. Its utilization rate is 9.59%.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.