EX8-7 (Algo) You are one of four carpenters assigned to... You are one of four c
ID: 348521 • Letter: E
Question
EX8-7 (Algo) You are one of four carpenters assigned to... You are one of four carpenters assigned to complete a short construction project. Right before the start of the project, one of your fellow carpenters was hospitalized and will not be available to work on the project. Develop a resource-constrained schedule to see how long the project will take with only 3 carpenters. Be sure to record the order in which you schedule the activities using the scheduling heuristics. Activities 1, 2, 3, 4, 5, 7, and 8 require 2 carpenters to complete. Activity 6 requires only 1 carpenter. No splitting of activities is possible. You will receive a bonus if the project is completed within 15 days 10 7 12 0 2 0 102 12 5 10 0 20 8 210 0 1 2 0 2 0 5 4 8 0 2 0 3 8 8 6 11 12 8 14 0 2 0 12 2 14 0 2 0 9 312 ES IDEF SLK RES SLK Schedule resource load chart with ES and slack updates 2 50 10o Resources scheduled Resources available Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. Any resource scheduled beyond the shaded area will delay the project. "TP" stands for time period List the order in which you scheduled the activities of the projectExplanation / Answer
As the completion time is 14 days, bonus will be received:
So Yes
From the ES LF and Slack we can decide the sequence ID Reason 1st 1 2nd 3 3rd 2 Slack of 2 4th 4 5th 5 6th 6 Slack of 1 7th 7 8th 8Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.