The president of a consulting firm wants to minimize the total number of hours i

ID: 348394 • Letter: T

Question

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows: Project (Hours) Conaultant A charlie Betty Johnay Rick 13 10 15 13 16 14 12 12 15 17 17 Assume there must be one-to-one matching between consultants and projects. After the row and column reductions, what is the resulting entry in the new table for assigning Rick to project D? 0 0 hours O 8 hours O 10 hours O 9 hours O 22 hours

Explanation / Answer

Assume there must be one to one matching between consultants and projects. After the row and column reductions, what is the resulting entry in the new table for assigning Rick to project D

9 Hours