Using PERT, Adam Munson was able to determine that the expected project completi
ID: 346759 • Letter: U
Question
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 2121 months, and the project variance is 1616. a) The probability that the project will be completed in 55 months = nothing (round your response to four decimal places). b) The probability that the project will be completed in 2020 months = nothing (round your response to four decimal places). c) The probability that the project will be completed in 2525 months = nothing (round your response to four decimal places). d) The probability that the project will be completed in 3737 months = nothing (round your response to four decimal places). e) The due date that yields a 95% chance of completion = nothing months (round your response to two decimal places).
Explanation / Answer
z - value = (Estimate Time - Expected Time/standard deviation
Expected Time = 2121
standard deviation = sqrt(Variance) = sqrt(1616) = 40.1995
a) Estimated Time = 55
z -value = (55-2121)/40.1995 = -51.3937
Probability with above z - value is 0.0000
b) Estimated Time = 2020
z-value = (2020-2121)/40.1995 = -2.5125
Probability with above z - value is 0.0060
c) Estimated Time = 2525
z-value = (2525-2121)/40.1995 = 10.0499
Probability with above z - value is 1.0000
d) Estimated Time = 3737
z-value = (3737-2121)/40.1995 = 40.1995
Probability with above z - value is 1.0000
Note - Probability can be calculated from z-table or using formula NORM.S.DIST in excel