1. An example of a firm using yield management in their services would be if Amt

ID: 346660 • Letter: 1

Question

1.

An example of a firm using yield management in their services would be if Amtrack were to price its train as follows:

Business Class with 20 seats at $_________ & Economy Class with 100 seats at $________

$1000 , $100

$1000, $1000

$100, $10000

$100, $1000 (buy one get one free)

2.

One way to reduce a queue is to reduce ________ during __________ times

Demand, off-peak

Demand, peak

Supply, off peak

supply, peak

3.

Imagine you receive an order to do 200 Hot Pot dishes in 2 hours. In addition you have 3 stations that all have a part in making the dish.

Station 1 = 10 Secs

Station 2 = 20 Secs

Station 3 = 10 Secs

Calculate the labor content

40 Seconds

100 minutes

60 Seconds

2.5 Minutes

Could you please be kind enough and show me the answers in detail? Thank you so much for reading this and have a good one!

$1000 , $100

$1000, $1000

$100, $10000

$100, $1000 (buy one get one free)

2.

One way to reduce a queue is to reduce ________ during __________ times

Demand, off-peak

Demand, peak

Supply, off peak

supply, peak

3.

Imagine you receive an order to do 200 Hot Pot dishes in 2 hours. In addition you have 3 stations that all have a part in making the dish.

Station 1 = 10 Secs

Station 2 = 20 Secs

Station 3 = 10 Secs

Calculate the labor content

40 Seconds

100 minutes

60 Seconds

2.5 Minutes

Could you please be kind enough and show me the answers in detail? Thank you so much for reading this and have a good one!

Explanation / Answer

1. An example of a firm using yield management in their services would be if Amtrack were to price its train as follows:

Business Class with 20 seats at $_________ & Economy Class with 100 seats at $________

Answer = $1000 , $100

2. One way to reduce a queue is to reduce ________ during __________ times

Answer = Demand, peak

3. Imagine you receive an order to do 200 Hot Pot dishes in 2 hours. In addition you have 3 stations that all have a part in making the dish.

Station 1 = 10 Secs

Station 2 = 20 Secs

Station 3 = 10 Secs

Calculate the labor content

Answer= The total labor content is defined as the time sum of all process steps

= Station 1 + Station 2 + Station 3

= 10 + 20 + 10

= 40 seconds