Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Score: 0 of 5 pts 10 of 10 (9 complete) HW Score: 66.67%, 10 of 15 Instructor-cr

ID: 345007 • Letter: S

Question

Score: 0 of 5 pts 10 of 10 (9 complete) HW Score: 66.67%, 10 of 15 Instructor-created question Question Help Time (weeks) Immediate Time (weeks) Immediate Activity m b Predecessors Activity a 23 10 bPredecessor(s) C, E 5 4 6 D, G, H 20 C, E a) The expected (estimated) time for activity C is 13.5 weeks. (Round your response to two decimal places.) b) The variance for activity C is 1.36 weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is A-C F-H-J - K d) The estimated time for the critical path is weeks. (Round your response to two decimal places.) e) The activity variance along the critical path is weeks. (Round your response to two decimal places.)

Explanation / Answer

Below table calculates expected duration as well as variance of each activity on the critical path :

Activity

Optimistic

Most likely

Pessimistic

Expected duration

Variance

A

6

9

12

9.00

1.00

C

9

14

16

13.50

1.36

F

5

9

20

10.17

6.25

H

2

2

2

2.00

0.00

J

6

7

12

7.67

1.00

K

1

1

4

1.50

0.25

SUM =

43.83

9.86

It is to be noted :

Expected duration of an activity = ( Optimistic duration + 4 x Most likely duration + Pessimistic duration ) / 6

Variance of an activity =     ( Pessimistic duration – Optimistic duration)^2/36

Thus sum of expected duration of all activities on critical path = 43.83 weeks

Sum of variances of all activities on critical path = 9.86 weeks

THE ESTIMATED TIME FOR THE CRITICAL PATH IS = 43.83 WEEKS

THE ACTIVITY VARIANCE ALONG THE CRITICAL PATH IS = 9.86 DAYS

Activity

Optimistic

Most likely

Pessimistic

Expected duration

Variance

A

6

9

12

9.00

1.00

C

9

14

16

13.50

1.36

F

5

9

20

10.17

6.25

H

2

2

2

2.00

0.00

J

6

7

12

7.67

1.00

K

1

1

4

1.50

0.25

SUM =

43.83

9.86

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote