The following table lists the components needed to assemble an end item, lead ti

ID: 343356 • Letter: T

Question

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand Amount on ItemT Direct Components (2), C(1), K(3) B (2), J (3) G (2), B (2) H(4), B (2) Hand End 16 21 29 30 o. If 43 units of the end item are to be assembled, how many additional units of B are needed? (int You don't need to develop an MRP plan) Additional units b. An order for the end item is scheduled to be shipped at the start of week 11 What is the latest week that the order can be started and still be ready to ship on time? (Hint You don't need to develop an MRP plan) The latest week ]

Explanation / Answer

One unit of end item requires 2 unit of L and each unit of L requires 2 units of B, making it 2 x 2 = 4 units of B for 1 unit of end item

One unit of end item requires 1 unit of C and each unit of C requires 2 units of B , making 1 x 2 = 2 units of B for 1 unit of end item

One unit of end item requires 3 units of K and each unit of K requires 2 units of B , making 3 x 2 = 6 units of B for 1 unit of end item

Thus total units of B required for 1 unit of end item = 4 + 2 + 6 = 12 units

Gross requirement of B for 43 units of end item = 43 x 12 = 516 units

However number of B units on hand = 29

Therefore , net requirement of B units = 516 – 29 = 487

ADDITIONAL UNITS = 487 UNITS

The cumulative lead time for various options consisting of “End item – Tier 1 item – Tier 2 item” are as follows :

End item – L – B = 2 + 2 + 2= 6 weeks

End item – L – J = 2 + 2 + 3 = 7 weeks

End item – C – J =2 + 3 + 3 = 8 weeks

End item – C – B = 2 + 3 + 2 = 7 weeks

End item – K – H = 2 + 3+ 2 = 7 weeks

End item – K – B = 2 + 3+ 2 = 7 weeks

Out of above , End item – C- J has the longest lead time of 8 weeks

Therefore latest week the order should be started so that end item can be shipped by week 11

= week 11 – week 8

= Week 3

THE LATEST WEEK = WEEK 3

ADDITIONAL UNITS = 487 UNITS