It takes the Blacksburg Shipyard 52 weeks with 165 workers to build a small tank
ID: 343232 • Letter: I
Question
It takes the Blacksburg Shipyard 52 weeks with 165 workers to build a small tanker. Material costs are $33 million and overhead costs are $2 million. Workers cost $17 per hour including benefits and work 40 hours per week. The ship sells for $56 million. To determine the multifactor productivity ratio, the spreadsheet shown below can be used (where yellow background is input, light green intermediate results and dark green the final result):
PLEASE ANSWER QUESTIONS A,B and C. Only indicate correct letter. No solutions needed.
a. A correct calculation of the Labor cost in cell C14 can be expressed as:
A.=C10
B.=C14+C15+C16
C.=C4*C5*C8*C9
D.=C10/C17
E.none of these
b. A correct calculation of the Total Input in cell C17 can be expressed as:
A.none of these
B.=C4*C5*C8*C9
C.=C10
D.=C14+C15+C16
E.=C10/C17
c. A correct calculation of the Multi-factor Productivity in cell E18 can be expressed as:
A.=C10
B.none of these
C.=C4*C5*C8*C9
D.=C14+C15+C16
E.=C10/C17
1 Blacksburg Shipyard 2 3 Data 4 time 5 # of workers 6 material cost 7 overhead cost 8 pay rate 9 work rate 10 Selling Price weeks our hours/week Dollar amounts below in mill ions 12 Output 13 Input 14 Labor 15 Material 16 Overhead 17 TOTAL 18 Multi-factor Productivity =Explanation / Answer
a) option C, C4*C5*C8*C9
total Labor cost = no. of weeks*no. of workers*pay rate*work rate
the rate at which they are paid multiplied by hours they work per week multipled by no. of weeks multiplied to no of workers.
b) option D.=C14+C15+C16
the total input cost is nothing but sum of labor, material and overhead cost
c) option E.=C10/C17
Multi-factor Productivity is amount of goods or sales produced to the amount of inputs used: selling price/total input