It cost a contractor $12,750 to manufacture their first unit. The company expect

ID: 3431903 • Letter: I

Question

It cost a contractor $12,750 to manufacture their first unit. The company expects to experience a 92% unit learning curve. Estimate the cost of the 10th unit. (Round intermediate calculations to 4 decimal places) A)   $15,661 B)   $9,665 C)   $10,380 D)   $11,985 It cost a contractor $12,750 to manufacture their first unit. The company expects to experience a 92% unit learning curve. Estimate the cost of the 10th unit. (Round intermediate calculations to 4 decimal places) A)   $15,661 B)   $9,665 C)   $10,380 D)   $11,985

Explanation / Answer

B) $9,665