It took a contractor 7000 hours to manufacture their first unit of an item. If t

ID: 3431902 • Letter: I

Question

It took a contractor 7000 hours to manufacture their first unit of an item. If the contractor expects to achieve a 94% unit learning curve, how many hours would be required to manufacture units 76-100? (Use the tables provided in the lesson). A)   507,683 B)   117,382 C)   507,717 D)   112,627 It took a contractor 7000 hours to manufacture their first unit of an item. If the contractor expects to achieve a 94% unit learning curve, how many hours would be required to manufacture units 76-100? (Use the tables provided in the lesson). A)   507,683 B)   117,382 C)   507,717 D)   112,627

Explanation / Answer

C) 507,717